Following repairs to IRDT's computer, we are now receiving very regular updates on the new Crakehall School building, together with photos. The new form of construction means that the walls are now going up very quickly, with panels being made from concrete poured into formers. Venkat has also been advised that the roof for the whole school will only take 6 days to make, compared to around 20 days using the old methods! Over 30 people are now being employed on site, and the engineer is paying a daily rate of 300 rupees making a significant impact on the cashflow for the villagers.
Opening the new school is scheduled for mid October- there still seems much to be done by then!